Resource Manager - Compliance report provides resource managers a single place to view Compliance status for various critical KPIs. All the KPIs are depicted in various visualizations.
Pending Approval: Scorecard that displays the # of resources whose timesheets are not approved.
Employee Type Counts: Pie chart displays the # of resources per employment type (Employee / Contractor)
Task Performance: Pie chart displaying # of resources per their below performance status.
Stale - Task finish date is less than today’s date
Critical – Task Baseline finish date is less than today’s date
Late – (Task Finish date – Task Baseline finish date) > 5
Early – (Task Baseline Finish date – Task finish date) > 5
On Time – (Task Baseline Finish date – Task finish date)